Construction at Violet Tower has reached 97.36% overall completion as of October 2026, marking an advanced stage of development. Major structural works are fully complete, with internal works, finishes, and building services nearing completion.
01
Superstructure nearing upper floors
Foundation, Substructure, and Superstructure works have reached 100%, with strengthening works completed.
02
Internal Finishes Near Completion
Internal Works and Internal Finishes have reached 97%, with Building Services progressing at 90%.
03
Key Inspections and Approvals
Empower inspection and FIC approval are complete, with DEWA electrical inspection approval pending.
Overall Completion
0%
Construction Progress
Site Mobilization
100%
Enabling Works
100%
Piling & Foundations
100%
Substructure
100%
Superstructure
100%
Internal Works
97%
External Envelope
95%
Building Services
90%
Internal Finishes
97%
External Works
80%
Infrastructure
93%
Project Progress Summary
Structural Construction Completed
All major structural activities have reached 100% completion, with additional strengthening works also confirmed as complete.
Interior and Building Services Progress
Internal Works and Internal Finishes have reached 97%, while Building Services stand at 90%, with MEP testing and commissioning underway.
Regulatory Inspections and Approvals
Empower inspection and FIC approval have been secured, while DEWA electrical inspection approval was targeted for 6 November 2026.
External and Courtyard Development
1. External Envelope works have reached 95%, with painting ongoing and courtyard works targeted for completion within two weeks of the report.
What's Next
01
Follow up on the DEWA electrical inspection approval targeted for 6 November 2026.
02
Continue MEP testing and commissioning alongside remaining building services activities.
03
1. Complete remaining courtyard works and progress external painting and finishing activities.
Q1 2027
Project Handover
Days
Hours
Minutes
Construction activities are progressing in line with the development schedule, with key milestones actively being achieved on site. We will continue to share regular updates to keep all investors informed of ongoing construction progress. All completion percentages and timelines are indicative and may be subject to change based on site conditions and construction requirements.