Construction is advancing toward the final stages, with ACP cladding nearly complete, curtain wall installation completed, and apartment tiling finished. Final external and internal painting, joinery, roof MEP works, courtyard waterproofing, and strengthening works are progressing across the development.
01
Superstructure nearing upper floors
Steel structure nearly complete with topping out imminent across the full tower height
02
Finishes Accelerating
Internal finishes at 50% with tile installation reaching the 19th floor
03
MEP at the Summit
MEP installation works have advanced all the way to the 27th floor
Overall Completion
0%
Construction Progress
Site Mobilization
100%
Enabling Works
100%
Piling & Foundations
100%
Substructure
100%
Superstructure
100%
Internal Works
80%
External Envelope
70%
Building Services
36%
Internal Finishes
89%
External Works
50%
Infrastructure
30%
Project Progress Summary
ACP cladding for the steel stractural Almost completed
Final Internal paint in progress
Tiles works at the apartments completed
Joinery works reached in the final stage
Curtain walls installation reached completed
Court yard waterproofing in the remaining area in progress
MEP works installation at roof in progress
Strengthening works in progress
What's Next
01
MEP works installation at roof in progress
02
Court yard waterproofing in the remaining area in progress
03
Strengthening works in progress
Q2 2026
Project Handover
Days
Hours
Minutes
Construction activities are progressing in line with the development schedule, with key milestones actively being achieved on site. We will continue to share regular updates to keep all investors informed of ongoing construction progress. All completion percentages and timelines are indicative and may be subject to change based on site conditions and construction requirements.