Violet Tower

Construction Updates

August 2026 Edition

Progress Overview

Construction is advancing toward the final stages, with ACP cladding nearly complete, curtain wall installation completed, and apartment tiling finished. Final external and internal painting, joinery, roof MEP works, courtyard waterproofing, and strengthening works are progressing across the development.

01

Superstructure nearing upper floors

Steel structure nearly complete with topping out imminent across the full tower height

02

Finishes Accelerating

Internal finishes at 50% with tile installation reaching the 19th floor

03

MEP at the Summit

MEP installation works have advanced all the way to the 27th floor
Overall
Completion
0%

Construction Progress

Site Mobilization
100%
Enabling Works
100%
Piling & Foundations
100%
Substructure
100%
Superstructure
100%
Internal Works
80%
External Envelope
70%
Building Services
36%
Internal Finishes
89%
External Works
50%
Infrastructure
30%

Project Progress Summary

ACP cladding for the steel stractural Almost completed

Final Internal paint in progress

Tiles works at the apartments completed

Joinery works reached in the final stage

Curtain walls installation reached completed

Court yard waterproofing in the remaining area in progress

MEP works installation at roof in progress

Strengthening works in progress

What's Next

01

MEP works installation at roof in progress

02

Court yard waterproofing in the remaining area in progress

03

Strengthening works in progress

Q2 2026

Project Handover

Days
Hours
Minutes
Construction activities are progressing in line with the development schedule, with key milestones actively being achieved on site. We will continue to share regular updates to keep all investors informed of ongoing construction progress. All completion percentages and timelines are indicative and may be subject to change based on site conditions and construction requirements.