Violet Tower

Construction Updates

September 2026 Edition

Progress Overview

Construction at Violet Tower has reached 90.15% overall completion, with all structural stages fully complete. Internal finishes are at an advanced stage, while final façade, MEP, external and infrastructure works continue across the development.

01

Superstructure nearing upper floors

Internal finishes have reached 92%, with final painting progressing up to the 27th floor.

02

Fit-Out Progress

Kitchen, vanity and wardrobe installations are complete, while wooden door installation has reached the 27th floor.

03

External Envelope Progress

ACP works are complete, with final painting across all elevations progressing toward expected completion by the end of October 2026.
Overall
Completion
0%

Construction Progress

Site Mobilization
100%
Enabling Works
100%
Piling & Foundations
100%
Substructure
100%
Superstructure
100%
Internal Works
85%
External Envelope
78%
Building Services
60%
Internal Finishes
92%
External Works
55%
Infrastructure
65%

Project Progress Summary

Façade Works

ACP works are complete, while final paint works across all elevations continue toward expected completion by the end of October.

Interior Fit-Out

Corridor tiling and kitchen, vanity and wardrobe installations are complete, with wooden doors reaching the 27th floor.

Balconies & MEP

Glass balustrade installation to balconies is almost complete, alongside MEP works at roof level nearing completion.

External Areas

Courtyard tiling preparation has commenced, while strengthening works have progressed to the ground floor.

What's Next

01

Progress final elevation painting toward the targeted end-of-October completion.

02

Complete remaining balcony glass balustrades and roof-level MEP installations.

03

Advance courtyard tiling and remaining external and infrastructure activities.

Q2 2026

Project Handover

Days
Hours
Minutes
Construction activities are progressing in line with the development schedule, with key milestones actively being achieved on site. We will continue to share regular updates to keep all investors informed of ongoing construction progress. All completion percentages and timelines are indicative and may be subject to change based on site conditions and construction requirements.
A Subsidiary of Dubai Investments