Danah Bay

Construction Updates

September 2026 Edition

Progress Overview

Construction at Danah Bay continues to advance across both towers. The Residential Tower has reached 59.8% completion, with its superstructure complete, while the Hotel Tower has reached 47.0%, with superstructure works at 95% and internal, façade and building services progressing.

01

Structural Milestones

Residential Tower superstructure is complete, while Hotel Tower superstructure has reached 95%.

02

Façade Progress

External Envelope works have reached 45% at the Residential Tower and 31% at the Hotel Tower.

03

Interior Works Advancing

Internal works are at 58% in the Residential Tower and 29% in the Hotel Tower, with finishing activities progressing across both towers
Hotel
Tower
0%
Residential
Tower
0%

Construction Progress

Hotel Tower

Site Mobilization
100%
Enabling Works
100%
Building Permit
100%
Piling & Foundation
100%
Substructure
100%
Superstructure
95%
Internal Works
29%
External Envelope
31%
Building Services
27%
Internal Finishes
16%
External Works
13%
Infrastructure
22%

Residential Tower

Site Mobilization
100%
Enabling Works
100%
Building Permit
100%
Piling & Foundations
100%
Substructure
100%
Superstructure
100%
Internal Works
58%
External Envelope
45%
Building Services
30%
Internal Finishes
58%
External Works
29%
Infrastructure
20%

Project Progress Summary

Residential Structure Complete

The Residential Tower has achieved 100% completion across piling, substructure and superstructure works.

Hotel Structure Advancing

Hotel Tower superstructure has reached 95%, bringing the building closer to full structural completion.

Façade Development

External Envelope works continue across both towers, reaching 45% at the Residential Tower and 31% at the Hotel Tower.

Interiors & Services

Internal finishes and building services continue progressing across both towers as construction moves further into fit-out stages.

What's Next

01

Progress the remaining Hotel Tower superstructure works toward full completion.

02

Continue façade, internal works and building services across both towers.

03

Advance internal finishes, external works and infrastructure throughout the development.

Q4 2027

Project Handover

Days
Hours
Minutes
Construction activities are progressing in line with the development schedule, with key milestones actively being achieved on site. We will continue to share regular updates to keep all investors informed of ongoing construction progress. All completion percentages and timelines are indicative and may be subject to change based on site conditions and construction requirements.