Danah Bay

Construction Updates

August 2026 Edition

Progress Overview

Construction at Danah Bay is advancing across both towers simultaneously, with the Residential Tower leading at 55.4% overall and the Hotel Tower at 44.5%. Superstructure works are active on both towers while internal fit-out and building services have commenced in the Residential Tower.

01

Dual Tower Momentum

Both towers progressing with active superstructure and early interior works underway

02

Residential Fit-Out Active

Internal works, building services, and external envelope all underway in the Residential Tower

03

Foundations Complete

All substructure and foundation works fully completed on both towers
Hotel
Tower
0%
Residential
Tower
0%

Construction Progress

Hotel Tower

Site Mobilization
100%
Enabling Works
100%
Building Permit
100%
Piling & Foundation
100%
Substructure
100%
Superstructure
90%
Internal Works
26%
External Envelope
27%
Building Services
25%
Internal Finishes
14%
External Works
12%
Infrastructure
20%

Residential Tower

Site Mobilization
100%
Enabling Works
100%
Building Permit
100%
Piling & Foundations
100%
Substructure
100%
Superstructure
100%
Internal Works
45%
External Envelope
38%
Building Services
25%
Internal Finishes
45%
External Works
25%
Infrastructure
10%

Project Progress Summary

Foundations Complete

All pre-construction and foundation works completed at 100% across both towers

Hotel Tower Rising

Superstructure actively progressing at 45% with upper floors under active casting

Residential Interior Active

Internal works at 14% with block work, plastering, and building services all underway

Early Works Initiated

Internal finishes commenced in the Hotel Tower while infrastructure works have begun in the Residential Tower

What's Next

01

Continue superstructure casting on both towers to advance upper floor levels

02

Expand internal works, MEP, and building services across the Residential Tower

03

Initiate external envelope and interior works on the Hotel Tower lower floors

Q4 2027

Project Handover

Days
Hours
Minutes
Construction activities are progressing in line with the development schedule, with key milestones actively being achieved on site. We will continue to share regular updates to keep all investors informed of ongoing construction progress. All completion percentages and timelines are indicative and may be subject to change based on site conditions and construction requirements.
A Subsidiary of Dubai Investments