Asayel Avenue

Construction Updates

October 2026 Edition

Progress Overview

Construction at Mirdif Asayel has reached 69.49% overall completion as of October 2026. All major structural activities are fully complete, with progress continuing across internal works, façade treatments, and building services.

01

Structural Works Complete

Piling & Foundation, Substructure, and Superstructure have reached 100% completion across the development.

02

Internal Works Progress

Internal Works have reached 60%, with plastering, board closing, and MEP second-fix installations underway.

03

Façade Development Advances

External Envelope works have reached 55%, with cladding, exterior painting, and plastering progressing.
Overall
Completion
0%

Construction Progress

Site Mobilization
100%
Enabling Works
100%
Piling & Foundations
100%
Substructure
100%
Superstructure
100%
Internal Works
60%
External Envelope
55%
Building Services
20%
Internal Finishes
50%
External Works
25%
Infrastructure
19%

Project Progress Summary

Structural Construction Completed

Piling & Foundation, Substructure, and Superstructure activities have all reached 100% completion, marking a key project milestone.

Façade and External Plastering

External cladding and painting works are progressing, while external plastering activities have reached the fifth floor.

Internal Finishes and MEP Installations

MEP second-fix installations are underway up to the fifth floor, with board closing activities started on the second floor.

Courtyard and Rooftop Activities

1. Courtyard works have commenced, alongside ongoing installation activities for mechanical, electrical, and plumbing services at roof level.

What's Next

01

Continue external cladding, painting, and plastering activities across the building elevations.

02

Advance MEP second-fix installations and board closing across the remaining floors.

03

1. Progress courtyard development and rooftop MEP service installations.

Q3 2027

Project Handover

Days
Hours
Minutes
Construction activities are progressing, with key milestones actively being achieved on site. We will continue to share regular updates to keep all investors informed of ongoing construction progress. All completion percentages and timelines are indicative and may be subject to change based on site conditions and construction requirements.