Construction is progressing steadily, with block works completed and elevation, cladding, aluminum, and glazing works underway. Internal works continue across multiple floors, including plastering, tiling, painting, MEP first and second fix, board closing, and suspension works.
01
Superstructure Rising
Slabs cast up to the 4th floor across all four construction zones
02
Block Work Underway
Block work active from basement through to second floor level
03
MEP First-Fix Initiated
MEP first-fix works started on the first floor, final fix at basement
Overall Completion
0%
Construction Progress
Site Mobilization
100%
Enabling Works
100%
Piling & Foundations
100%
Substructure
100%
Superstructure
100%
Internal Works
38%
External Envelope
41%
Building Services
15%
Internal Finishes
31%
External Works
25%
Infrastructure
17%
Project Progress Summary
MEP works second fixed onging at till 2nd floor
Zones 1 and 3 reached 3rd slab level; Zone 2 achieved 4th slab; Zone 4 reached third floor
Block Work & Plaster Active
Block work running from basement to second floor; plastering initiated on the first floor
MEP First-Fix Underway
MEP first-fix active on the first floor; high-level final fix commenced at basement level
External Envelope Initiated
External envelope works have commenced at 1%, marking the beginning of facade activities on site
What's Next
01
Continue superstructure casting to upper floor levels across all zones
02
Extend block work and plaster works progressively to higher floors
03
Progress MEP installations floor by floor in line with superstructure advance
Q4 2027
Project Handover
Days
Hours
Minutes
Construction activities are progressing in line with the development schedule, with key milestones actively being achieved on site. We will continue to share regular updates to keep all investors informed of ongoing construction progress. All completion percentages and timelines are indicative and may be subject to change based on site conditions and construction requirements.