Asayel Avenue

Construction Updates

September 2026 Edition

Progress Overview

Construction at Asayel Avenue continues to advance, reaching 60.09% overall completion. Structural works are fully complete, while façade, internal finishes, MEP services and external works continue progressing across the development.

01

Structural Works Complete

Piling & Foundation, Substructure and Superstructure works have all reached 100% completion.

02

Internal Works Advancing

Plaster works are almost complete, while tiling and painting activities have progressed to the fourth floor.

03

Façade & MEP Progress

Elevation works continue alongside second-fix MEP works progressing up to the fourth floor.
Overall
Completion
0%

Construction Progress

Site Mobilization
100%
Enabling Works
100%
Piling & Foundations
100%
Substructure
100%
Superstructure
100%
Internal Works
40%
External Envelope
45%
Building Services
15%
Internal Finishes
36%
External Works
25%
Infrastructure
19%

Project Progress Summary

Structure Complete

The development's piling, foundation, substructure and superstructure works have achieved 100% completion.

Interior Works

Plaster works are nearing completion, with tiling almost complete up to the fourth floor and painting reaching the fourth floor.

MEP & Ceiling Works

Second-fix MEP works are progressing up to the fourth floor, with board closing and suspended ceiling works underway at the first floor.

Roof Waterproofing

Waterproofing activities have commenced at roof level as finishing and building service works continue across the project.

What's Next

01

Continue elevation works as the external envelope progresses across the development.

02

Advance internal tiling, painting, MEP second-fix and suspended ceiling works.

03

Progress roof waterproofing alongside ongoing internal and external finishing activities.

Q4 2027

Project Handover

Days
Hours
Minutes
Construction activities are progressing in line with the development schedule, with key milestones actively being achieved on site. We will continue to share regular updates to keep all investors informed of ongoing construction progress. All completion percentages and timelines are indicative and may be subject to change based on site conditions and construction requirements.