Construction is progressing steadily, with tower crane foundation casting, waterproofing, and substructure block works currently underway. Delivery of the tower crane sections is also in progress, supporting the next phase of construction.
01
Enabling Works Complete
All five enabling work activities have reached 100% completion on site
02
Site Clear & Ready
Enabling contractor has been fully demobilized, leaving the site prepared for main works
03
Foundation Phase Done
Piling, shoring, and excavation works all completed and signed off
Overall Completion
0%
Construction Progress
Site Mobilization
100%
Piling Works
9%
Shoring Works
0%
Excavation Works
0%
Demobilization
0%
Project Progress Summary
Enabling Works Finalized
All site enabling works completed at 100%, with no outstanding activities remaining
Contractor Demobilized
The enabling contractor has been fully demobilized and cleared from site
Site Ready for Main Works
The site is fully prepared for the appointment and mobilization of the main contractor
Shoring Activities
Procurement for the main contractor appointment is the immediate next step for the project
What's Next
01
Tower crane foundations casting in progress
02
Water proofing works in progress
03
Substractural block works in progress
Q1 2028
Project Handover
Days
Hours
Minutes
Al Vista continues to progress steadily through its early construction phases, with key groundwork milestones achieved this month. Regular updates will be shared as works advance. Timelines provided are indicative and may be subject to change based on site conditions and construction requirements.