Progress Overview

Construction at Al Vista continues to advance, with overall completion reaching 9.45%. Site Mobilization and Enabling Works are fully complete, while foundation and substructure activities are progressing across Towers A and B.

01

Foundation Works Advancing

Piling & Foundation works have reached 25%, supporting continued structural progress.

02

Tower A Milestone

All pile caps for Tower A have been cast, with steel works for Raft A currently in progress.

03

Tower B Progress

Pile cap steel works for Tower B have reached 70%, while waterproofing works are 50% complete.
Overall
Completion
0%

Construction Progress

Site Mobilization
100%
Piling Works
25%

Shoring Works

0.1%
Excavation Works
0.1%
Demobilization
0.1%

Project Progress Summary

Site Preparation Complete

Site Mobilization and Enabling Works have reached 100%, establishing the groundwork for structural activities.

Tower A Foundations

All Tower A pile caps have been cast, with Raft A steel works currently progressing on site.

Tower B Foundations

Steel works for Tower B pile caps have reached 70%, marking continued progress across the foundation stage.

Shoring Activities

Steel works for Raft A are underway, with casting expected to take place by 10 October 2026.

What's Next

01

Complete Raft A steel works and proceed with the planned raft casting.

02

Continue Tower B pile cap steel works toward full completion.

03

Advance waterproofing works beyond the current 50% completion level.

Q1 2028

Project Handover

Days
Hours
Minutes
Al Vista continues to progress steadily through its early construction phases, with key groundwork milestones achieved this month. Regular updates will be shared as works advance. Timelines provided are indicative and may be subject to change based on site conditions and construction requirements.