Al Vista

Construction Updates

October 2026 Edition

Progress Overview

Construction at Al Vista Meydan has reached 13.30% overall completion as of October 2026. Site mobilization and enabling works are fully complete, while foundation and substructure activities continue across the development.

01

Site Preparation Complete

Site Mobilization and Enabling Works have both reached 100%, supporting continued construction progress.

02

Tower A Foundation Milestone

Tower A’s raft foundation and pile caps have been cast, marking a key construction milestone.

03

Tower B Foundation Progress

Raft reinforcement works are underway, with pile cap steel works reported at 70% completion.
Overall
Completion
0%

Construction Progress

Site Mobilization
100%
Piling Works
50%
Shoring Works
0.1%
Excavation Works
0.1%
Demobilization
0.1%

Project Progress Summary

Site Mobilization & Enabling Works

Site Mobilization and Enabling Works have reached 100% completion, establishing the groundwork for subsequent construction activities.

Tower A Foundation Completion

Tower A's raft foundation has been cast, alongside the completion of its pile caps, marking an important structural milestone.

Tower B Foundation Activities

Tower B's raft reinforcement works are progressing, while steel works for its pile caps have reached 70% completion.

Shoring Activities

1. Substructure works have reached 45% completion, with Superstructure activities also underway at 2% overall progress.

What's Next

01

Continue Tower B raft reinforcement works ahead of the targeted concrete casting on 15 November 2026.

02

Advance the remaining Tower B pile cap steel works beyond the currently reported 70% completion.

03

1. Continue foundation and substructure activities to support subsequent superstructure construction.

Q1 2029

Project Handover

Days
Hours
Minutes
Al Vista continues to progress steadily through its early construction phases, with key groundwork milestones achieved this month. Regular updates will be shared as works advance. Timelines provided are indicative and may be subject to change based on site conditions and construction requirements.
A Subsidiary of Dubai Investments