Construction at Danah Bay continues across both towers, with the Hotel Tower reaching 51.7% and the Residential Tower achieving 68.0% completion. All major structural works are complete in both towers, while façade installation, internal works, building services, and finishing activities progress across the development.
01
Structural Works Complete
Both towers have reached 100% completion across foundation, substructure, and superstructure works.
02
Residential Tower Progress
Internal Works have reached 70%, with External Envelope works at 60% and Internal Finishes at 40%.
03
Hotel Tower Development
External Envelope works have reached 42%, alongside 38% Internal Works and 29% Building Services.
Residential Tower
0%
Construction Progress
Residential Tower
Site Mobilization
100%
Enabling Works
100%
Building Permit
100%
Piling & Foundations
100%
Substructure
100%
Superstructure
100%
Internal Works
70%
External Envelope
60%
Building Services
50%
Internal Finishes
70%
External Works
35%
Infrastructure
38%
Project Progress Summary
Structural Construction Completed
Both the Hotel and Residential Towers have achieved 100% completion of piling, foundation, substructure, and superstructure works.
Residential Tower Interior Development
Internal Works have reached 70%, with inspection photographs showing progress in apartment kitchens, bathrooms, and interior spaces.
Hotel Tower Façade and Interior Progress
External Envelope works stand at 42%, with internal partitions, ceiling works, and façade glazing visible in site photographs.
Building Services and External Development
1. Building Services have reached 50% in the Residential Tower and 29% in the Hotel Tower, with further installation activities underway.
What's Next
01
Continue External Envelope and façade installation activities across both towers.
02
Advance Internal Works, finishing activities, and Building Services installations.
03
1. Progress External Works and Infrastructure activities across the development.
Q1 2027
Project Handover
Days
Hours
Minutes
Construction activities are progressing, with key milestones actively being achieved on site. We will continue to share regular updates to keep all investors informed of ongoing construction progress. All completion percentages and timelines are indicative and may be subject to change based on site conditions and construction requirements.