Construction Updates

August 2026 Edition

Progress Overview

Construction is progressing steadily, with tower crane foundation casting, waterproofing, and substructure block works currently underway. Delivery of the tower crane sections is also in progress, supporting the next phase of construction.

01

Enabling Works Complete

All five enabling work activities have reached 100% completion on site

02

Site Clear & Ready

Enabling contractor has been fully demobilized, leaving the site prepared for main works

03

Foundation Phase Done

Piling, shoring, and excavation works all completed and signed off
Overall
Completion
0%

Construction Progress

Site Mobilization
100%
Piling Works
9%
Shoring Works
0%
Excavation Works
0%
Demobilization
0%

Project Progress Summary

Enabling Works Finalized

All site enabling works completed at 100%, with no outstanding activities remaining

Contractor Demobilized

The enabling contractor has been fully demobilized and cleared from site

Site Ready for Main Works

The site is fully prepared for the appointment and mobilization of the main contractor

Shoring Activities

Procurement for the main contractor appointment is the immediate next step for the project

What's Next

01

Tower crane foundations casting in progress

02

Water proofing works in progress

03

Substractural block works in progress

Q1 2028

Project Handover

Days
Hours
Minutes
Al Vista continues to progress steadily through its early construction phases, with key groundwork milestones achieved this month. Regular updates will be shared as works advance. Timelines provided are indicative and may be subject to change based on site conditions and construction requirements.